This week on the Lake House:

We delivered all the sheetrock - 175 boards of 12 foot long

Boomed the sheetrock into the second floor .

JAFCO delivered the sheetrock , they did a great job and on time, thanks guys.

Johnny G Tile laid down the subfloor.  Comes all the way up from Belmar. Johnny came over for dinner afterwards.

Bravo's craftsmanship in one day.  3 crews , what a team. 

Bravo Construction came over and did the stone exterior.  They really lived up to their name .. Bravo !  They did the wire lath , then a scratch coat of cement, then they put on the stone.  Natural stones , various large sizes.